I. NEW RENTAL

Distributor Responsibility to:

a. Issue a written purchase order to include: rental rate, start date, and estimated usage.
b. Distributor to sign and return the Proweld Rental Agreement. Machines will not ship until Asahi/America receives this document.
c. Absorb freight costs to the jobsite unless it can be shipped with a freight allowed pipe order.
d. Place orders for machines at the time the material is ordered.

Asahi/America’s Responsibility to:

a. Ship machine within five working days from receipt of order, if available.
b. Advise distributor in writing of any delays in shipment.
c. Supply all machines with:

  • Operating instructions
  • Power requirements
  • Checklist of items sent
  • Two sets of sharp planer blades (not new). All blades sent must be returned or absorb replacement costs. Additional blades must be purchased.

II. MACHINE TRANSFERS (Site to Site)

The transfer of equipment from one job site to another is not recommended and should be avoided unless there is an emergency situation. Prior approval is required and use of the following procedure should be followed when transferring equipment:

Distributor Responsibility to:

a. Notify Asahi/America rental department of your intentions.
b.Provide all pertinent serial numbers and the last billing date for the current rental period.
c.Evaluate the machine for damages, missing parts, and functionality notifying your customer and Asahi/America.
d. Absorb costs for repairs and part replacement. Note our contract is with the distributor, making reimbursement your responsibility.
e. Issue a new purchase order with new start date, rental rate and estimated usage.
f.  Return a new Proweld Rental Agreement properly completed and signed.

Asahi/America Will:

a. Not authorize transfer of its equipment unless the above procedure is followed.
b. Not authorize transfer of equipment between distributor without written authorization to Asahi rental department.
c. Will only offer the 6 months of onsite warranty from start date of original rental date, transfers after the 6-month warranty start date, should be avoided as the tool may require needed maintenance. Tools shipped site to site within the 6-month warranty, may lose the warranty as tool condition is unknown. Paid inspections and maintenance are available for tools with unknown condition and status.

III. EQUIPMENT RETURNS

Distributor Responsibility to:

a. Obtain an RMA # from Asahi/America’s rental department at 781-388-4623. Rental billing stops the day tools are loaded onto return truck providing you forward copy of signed bill of lading (otherwise it stops day it hits our door).
b. Include on the distributor’s packing slip:

  • RMA number
  • Serial number of each machine
  • Description of item being returned

c.Equipment should be received back to Asahi/America within allotted timeframe from receipt of RMA number. East coast: 5 days; Central: 5-7 days, West coast: 7-10 days.
d. Absorb additional rental charges if equipment is not sent back within the prescribed time frame above.
e. Incomplete equipment returned without major working parts (clamps, heater, etc.) may be placed back on rental until all parts are received back.
f. Absorb freight charges on all equipment being returned.
g. Equipment must be properly packed up and travel locks applied to avoid any damage in transit that would be billed.

IV. REPAIRS AND PART REPLACEMENTS ON RETURNED EQUIPMENT

Asahi/America Will:

a. Assess all returned equipment for damage and missing parts.
b. Send a written evaluation of charges to the distributor and a notice to invoice. (Note: charges will include an hourly labor charge for repair when applicable)
c. Not bill for damages considered to be normal wear and tear such as:

  • Chains
  • Blades
  • Belts
  • Sprockets
  • etc.

d. Bill for re-coating heating elements that are returned having excessive scratches or surface damage.
e. Bill for damages caused by improper use or Insufficient pack-up by end user, causing damage in transit for return.

V. EQUIPMENT FAILURE IN THE FIELD

Distributor Responsibility to:

a. Advise Asahi/America rental department of the failure.
b.  Call Equipment Manager, Dave Hume, 617-306-4182 to troubleshoot any functionality issues.
c. Issue a purchase order for the replacement part at its full value.
d. Request an RMA for return of the damaged part and return promptly.

Asahi/America Will:

a. Ship replacement parts, air freight to the job site, if available.
b. Evaluate damaged parts and determine if the failure resulted from contractor abuse or mechanics.
c. Notify the distributor in writing of the results of our evaluation and of our intent to bill.
d. In the event of contractor abuse, all air freight and all associated repair costs will be applied to the existing purchase order.
e. In the event the failure is attributed to machine quality, any charges for replacement parts will be credited in full.
f. Issue a billing replacement costs for equipment returned without its original shipping crate.

VI. PURCHASE OF RENTAL EQUIPMENT OPTION

  • Only applies to approved equipment for sale.
  • Intent to buy must be agreed upon prior to shipping out.
  • A % of rental cost can be applied to the purchase of the rental unit, upon review at start of rental agreement.
  • Standard purchase price is typically the list less 40% for a used tool.
  • Standard purchase price is typically the list less 30% for a new tool. A tool that is rented for the first time to a project will be purchased as a new tool.
  • Rental monies can only be applied to the purchase of the machine being rented. Tools returned and later re-rented do not apply.
  • Rental monies are monitored by the distributor.
  • No credits will be issued in the event rental fees exceed the cost of the machine out on job.
  • Ownership transfers once all rental invoices are paid in full.
  • All machines purchased under this option carry a 90-day warranty on parts and labor from date of purchase if returned to Asahi for tune up evaluation (all freight and replacement parts are responsibility of the end user)

VII. BILLING PROCEDURES FOR RENTAL EQUIPMENT

  • Billings will be processed monthly using the following bill structure below.
  • All purchase orders submitted must indicate what rate you want to be billed at. Asahi does not monitor or change your rate. If you want to change your rate structure you can do so by notifying our rental department in writing. No credits are offered for past billings, new rate will be in current month and beyond.
  • Rental Rates:
    • Weekly: Calendar week or any part of. Partial weeks are pro-rated divided by 7. Rental charges include weekend and holidays.
    • Monthly: Agreed monthly rate will be billed whether 28, 30, or 31 days are in the month. Only partial months will bill at rate divided by 30.

Rental Minimums:

ALL high purity equipment (SP-63, SP 110-S V3, SP 250-S V3, SP 315-S, SP 110-B, EF 110-B) as well as Field 20 and Field 24 machines will rent at a five-day minimum.

VIII. FREIGHT

Customer pays freight from factory to the jobsite and jobsite to factory. No exceptions. Asahi will attempt to combine machines with freight allowed orders but won’t guarantee this service.

IX. DELIVERY

Asahi/America requires five (5) working days to ship a machine from receipt of order. Consult Asahi/America for expedited delivery.

X. ENCLOSURES

XI. WARRANTIES

All rental equipment is warranted for six (6) months of on-site usage. All tool failures within this six-month period are handled as indicated in Section V. After six months usage it is recommended that the equipment be returned for regular maintenance and warrantee renewal. Equipment held longer than six months without return is held at the renter's risk.

Purchase of refurbished/used equipment carries a 90-day warranty.

Purchase of brand-new equipment carries a one-year limited manufacturing warranty.